Among many preparations for the first Connect Care launch later this year are Launch Readiness Assessments (LRA). These bring together all participants in the Connect Care initiative to report on progress and problem-solve impediments. Each LRA spans the better part of a day, with rapid updates from diverse groups. This taking-the-temperature is invaluable for nimble adjustment and collaborative coordination.
LRAs are scheduled for 150, 120, 90, 60 and 30 days pre-launch. Our 120 day LRA occurs next week. Participants from across the province will meet to review each stream of work for their current state of readiness, identify potential risks and share ideas on how to mitigate those risks.
To learn more about readiness activities, visit the Connect Care Readiness page on Insite.